EQB logo
Buildings Demography Environment GIS Information Policy Technology Transportation More subjects

Project: Glencoe Light and Power 115 kV Transmission Line and Substation (11-162)

Contact: Ray Kirsch, 651-539-1841; None

PUC Docket Number: E241/LR-11-162

Local Review Notice

Notice by the Glencoe Light and Power Commission (GLPC) that they are seeking local review to construct a new 4.5-mile long 115 kilovolt (kV) transmission line and associated substation.  The new transmission line and substation would be located in McLeod County; the transmission line would pass through the city of Glencoe.

OES Response Letter

Letter from the Department of Commerce, Office of Energy Security (OES), confirming that GLPC's proposed project qualifies for local review and recognizing McLeod County as responsible for the environmental review process.

Environmental Assessment

The environmental assessment prepared by McLeod County for GLPC's 115 kV transmission line and substation project.  

Environmental Quality Board, 520 Lafayette Road North, Saint Paul, MN 55155

Technical problems? Contact: demography.helpline@state.mn.us